Project Awarded in Rawalpindi Division

 

Project No: Package No. 01
Implementation Agency : Punjab Aab-e-Pak Authority 

The Punjab Aab-E-Pak Authority (PAPA) intends to install Pre-filtration & Reverse Osmosis Water Treatment Plants for Rawalpindi Division of Pakistan. For water Treatment Plant for drinking purpose, raw water will be supplied from bore hole pump to the Water Treatment Plant where the water will be treated in accordance with the water quality. The treated water will be pumped up to each low-level reservoir (LLR) at the Markaz e Aab centers. The Contract includes a minimum of One (01) year operation and maintenance (O&M) period extendable by mutual agreement with the Contractor.

Contract Award Date: 04-06-2021 
Project Implementation Period (Start Date and End Date): 04 June 2021– 04 December 2021

Project cost and Project Awarded at Cost: PKR 275,306,168/-
Financing : Government of Punjab (100%)